Since the last update 6 cabinets went live enabling over 1,613 more homes and businesses across Leicestershire. If you want to be the first to hear about the latest project progress sign up to our emails here.
Cabinets now live:
- Cabinet 1 on the BAGWORTH exchange
- Cabinet 2 on the FLECKNEY exchange
- Cabinet 1 on the WELFORD exchange
- Cabinets 3 & 6 on the NETHER BROUGHTON exchange
- Cabinet 10 on the SAPCOTE exchange
Bagworth – Main St (Thornton)
Fleckney – Saddington Rd (Mowsley)
Welford – Welford Rd (South Kilworth)
Nether Broughton – near to the cemetery (Old Dalby) and Wartnaby Rd (Ab Kettleby)
Sapcote – Leicester Rd (Sapcote)
Cabinets encountering problems:
Leire 5 (Claybrooke Magna) – Work is slowly progressing in Claybrooke Magna. Some of the fibre has been blown (air pressure used to force fibre cables along the ducts) and Openreach have begun working on clearing the blockages. We are on track for the work to be completed by the end of May.
Market Bosworth 5 (Barlestone) – The remainder of the main fibre network (spine) is being built and the team are still hopeful for June
Stoke Golding 7 (Higham on the Hill) – BT engineers are still investigating the problems and hope to have some more information on the next steps forward early next week.
Please be aware that these dates are subject to change depending on the individual situation. The Superfast Leicestershire team will continue to keep you updated with the latest changes. Sign up here or follow the Twitter updates using the hashtag #SuperfastLeics.